TP-1000 (ENERGY SERVICES)


INTRODUCTION

OES is working in partnership with Shanghai Electric Power T&D Engineering Co. Ltd., China and is providing one window solution for all local works on the biggest T&D project by K-Electric called TP-1000. A team of 50+ professionals is looking after this project.

Main activities include:

  • Acquiring Right of Way for the complete project.
  • Project Monitoring & Management for the following construction activities:
  • Overhead Transmission Line 132 & 220 KV (63 km)
  • Underground Transmission Line 132 & 220 KV (28 km)
  • Complete Civil works (Trial Pits, Construction of Towers/Poles Foundations including construction materials, labour, machinery, tools, facilities, foundation tests etc.)
  • Erection & installation works (Erection of Towers/Poles/Gantries, Stringing of Conductors/OPGW, Excavation, Laying of Power Cables/FOC and Backfilling (In all respect)
  • Material Management of:
  • Storage
  • Logistics
  • Testing and Commissioning of Transmission Line (including Load and Environmental Tests)
  • Energization, handing over and after sales services for defects liability period and all necessary work to complete TP-1000 TL Project as per KE specifications.
ENERGY SERVICES EXPERTISE

OES is collaborating with TBEA Shandong Luneng Taishan Cable Co. Ltd. (TBEA), one of the biggest Chinese multinational groups for serving High Voltage Segment, OES together with TBEA, is providing turnkey solutions and services in Power transmission and distribution (T&D) segments. OES & TBEA Consortium is also approved by K-Electric for complete Underground Transmission Line works.

UNDERGROUND TRANSMISSION LINE

Expertise in the supply, cable laying, jointing, termination, erection, testing, commissioning and energization of Underground Transmission line up to 500kV voltage level for up to 2500 square mm XLPE cable circuit. Supply of imported XLPE cable and accessories from TBEA and other reliable manufacturers. Foreign jointers combined with local expertise provide the competitive advantage to carry out major EPC projects in Pakistan’s market.

OVERHEAD TRANSMISSION LINE

Expertise in the supply, stringing, erection, installation, testing, commissioning and energization of Overhead Transmission lines up to 500kV voltage level. This includes offshore part in the supply of Towers / Poles, insulators and their hardware with the onshore part starting from foundation works until final commissioning.

MAJOR PROJECTS INVOLVEMENT IN TRANSMISSION SEGMENT
S.NO CLIENT WORK DESCRIPTION
1 K-Electric (Project TP-1000-02) Execution of KE TP-1000-02 Project including Right of Way, Civil Works, Erection and Installation, Testing, Commissioning and Energization  of 132kV and 220kV Overhead and Underground Transmission Lines
2 Siemens Pakistan Design, Engineering, Supply, Laying, Erection, Installation, Testing, Commissioning and Energization of 132KV  Cable from Mauripur Grid Station to Lyari Grid Station
3 Pak Elektron Limited (PEL) Obtaining Right of Way, Erection and Installation, Testing, Commissioning and Energization  of 132kV Underground Transmission Line from KTGS to Getz Pharma Grid Station
4 Pak Elektron Limited (PEL) Installation services for 132 kV XLPE 800 sqmm Cable Sudkabel Terminations (Getz Pharma project)
5 K-Electric Supply and installation of Single core 500 sqmm PVC Power Cable at KE BQPS-1
6 K-Electric Supply & Installation Services for 220 kV XLPE 1400 sqmm Cable straight through Joint & Cable Termination for Underground TL.